As the new Creativity+Technology Center rises in place of the former Humanities Building, we thought you might want to track its progress.
As the new Creativity+Technology Center rises in place of the former Humanities Building, we thought you might want to track its progress. Here is a month-by-month digest of construction news.

February 2020
In February, the lower level ceiling structural system of trusses and beams was completed. Once the structure was ready, workers began installing plywood sheeting for the second floor. More than 100 tons of concrete were used to form the perimeter of the north stairway, much of which will be buried in grade. 

January 2020
Wood framing of interior walls progressed on the lower level. Prefabricated wall panels accelerated the pace. Heating and air conditioning, plumbing, and electrical trades moved in behind the framers to install building systems on the first floor. Concrete crews formed interior walls surrounding the elevator as well as curved, terraced seating levels in the Lecture and Symposium Hall. 

December 2019
Working one half of the area at a time, a team of 20 concrete workers placed concrete for the lower floor slab. That work was completed during Winter Break. The first batch of structural steel columns was installed. Workers applied waterproofing to the vertical concrete on the outside of the retaining walls to prepare for earth backfill.  

November 2019
A crane lifted forms for the concrete retaining walls into place and crews poured 11 truckloads of concrete into the forms to create the eastern perimeter of the lower floor. Workers relocated the forms to create the walls of the terraced lecture hall. 

October 2019
As the concrete footing pours continued, the crews began forming the cast-in-place concrete walls. Most of the under-slab plumbing and electrical lines were installed. 

September 2019
Concrete pumper trucks arrived this month and began pouring the retaining wall footings. 

August 2019
The County of Ventura issued the final building permit mid-August, clearing the way for construction to progress in earnest. While crews excavated for the new footings, an archaeologist and a Native American monitor watched for artifacts in the excavated dirt.

July 2019
Crews completed demolition of  the Humanities Building and continued building temporary classrooms in the Hills dining hall in July. 

June 2019
Structural demolition of the Humanities Building and the relocation of underground utilities began in June. Repurposing of the Hills dining area for temporary classrooms (as an interim replacement for those demoed in Humanities) began.

May 2019
While students were away on Extra Day Trips, the Anson S. Thacher Humanities Building was emptied and construction fencing installed around the site perimeter to prepare for demolition. Crews dismantled the interior of the building and salvaged what was salvageable. 
Back
Back-to-School Playbook for the 2020-2021 School Year
The Thacher School
5025 Thacher Road
Ojai, California, 93023

Tel : 805-646-4377

Notice of nondiscriminatory policy as to students: The Thacher School admits students of any race, color, national, and ethnic origin to all the rights, privileges, programs, and activities generally accorded or made available to students at the School. It does not discriminate on the basis of race, color, national, and ethnic origin in administration of its educational policies, admission policies, scholarship and loan programs, and athletic and other School-administered programs.